Class ZA – Demolition of buildings & construction of new flats or a house

 

Class ZA allows for the demolition of either a single purpose built detached block of flats or a single detached building within B1 Use Class that was existing on 12th March 2020 and it’s replacement with either a single propose built block of new flats or a single purpose built house with up to 2 additional storeys for the new structure in the airspace. B1 includes offices and light industrial. Note that this relates to the old B1 and not the new Use Class E

The new class allows for the demolition and construction of the new building including a basement or cellar. Importantly the footprint of the existing building must not exceed 1,000m², you cannot demolish part of a building or more than one building.

The maximum height of the old building including radio masts and antennae is 18m. The building must have been constructed on or before 31st December 1989.

The new building can have as many storeys as the old building plus two new ones in the airspace as long as the overall height is not increased by more than 7m or a maximum of 18m overall.

The new building or house will not benefit from Part 1 of the GPDO, development within the curtilage of a house.

Once complete you cannot change the single house or any of the flats in the block to C4 HMO using Class L. They must remain residential C3 unless full planning is obtained.

See our useful table of all airspace opportunities available within the GPDO.

Class ZA new flats

 

What else might prevent me taking advantage?

 

You cannot use this permitted development right of Class ZA in Article 2(3) land, SSSIs, listed buildings,  scheduled monuments, safety hazard area, military explosives area or within 3 kilometres(1.86 miles) of an aerodrome. Article 2(3) land includes conservation areas.

There are quite a few considerations that the local authority will need to consider as part of the prior approval for Class ZA.

These are transport & highways, air traffic and defence assets (if increasing in height), contamination, flood risk, external appearance, design of the new building, natural light in all habitable rooms, impacts of noise from any commercial premises on the intended occupiers, impact on increased residential user in the local area, impact on the development of heritage and archeology, landscaping, method of demolition,  impact upon amenity space of the existing building and neighbouring ones, overlooking/privacy/loss of light, impact on a protected view identified in the Directions Relating to Protected Vistas.

 

Application

Class ZA requires a Prior Approval application to the local authority and will be decided within 8 weeks or 56 days. You will also need to submit a flood risk report if required and information on the various considerations that the local authority will need to consider listed above.

The developer will also need to supply a report for the management of the construction of the development, which is acceptable to the authority and sets out the method of demolition, the proposed development hours of operation and how any adverse impact of noise, dust and vibration and traffic on occupiers of the new building and adjoining owners or occupiers will be mitigated, the proposed use of materials, and the plans for the disposal and recycling of waste generated by the development and that in carrying out the development the developer must comply with the report.

Also see the explanatory notes and in particular paragraphs 7.5 to 7.25.


Full legislation 

 

The full legislation issued on 30th July says…..

Class ZA New dwellinghouses on detached blocks of flats

Permitted development

ZA.—(1) Development consisting of works for the demolition of one or other of—
(a) any building comprising a single purpose-built detached block of flats, and
(b) any other single detached building, comprising premises established—
(i) for office use falling within Class B1(a) of the Schedule to the 1987 Order,
(ii) for research and development falling within Class B1(b) of the Schedule to the 1987 Order, or
(iii) for an industrial process falling within Class B1(c) of the Schedule to the 1987 Order,
or for any combination of them, existing on 12 March 2020, together with its replacement by a single building covered by sub-paragraph (2), involving operations listed in sub-paragraph (3).

(2) The building in question is to comprise one or other of—
(a) a purpose-built detached block of flats, or
(b) a purpose-built detached dwellinghouse.

(3) The operations in question are—
(a) operations reasonably necessary for the demolition and construction, which may include the installation of a basement or cellar in the new building, whether or not there is one in the old building;
(b) works for the removal of plant servicing the old building;
(c) works for the disconnection of services from the old building;
(d) works for the removal of any means of access to and egress from the old building;
(e) works for the removal of storage and waste from the old building;
(f) works for the installation of plant to service the new building;
(g) works for the installation of services to be connected to the new building;
(h) works to enable access to and egress from the new building, including means of escape from fire;
(i) works for the construction, within the new building, of storage, waste or other ancillary facilities to support the new building;
(j) the use of scaffolding and other temporary structures to support the operations listed in paragraphs (a) to (i) over a period—
(i) starting with their installation no earlier than one month before the beginning of those operations, and
(ii) ending with their removal no later than one month after the completion of those operations.

(4) In relation to Class ZA— “development” includes any change of use from the use of the old building to the use of the new building within Class C3 of the Schedule to the 1987 Order;
“the 1987 Order” means the Use Classes Order as in force on 12 March 2020;
“the old building” and “the new building” respectively mean the building proposed for demolition and the building proposed as replacement; and “services” means water, drainage, electricity, gas, and other services to the extent reasonably necessary for the new building to function as the building in question as defined by sub-paragraph (2) above.

Development not permitted

ZA1. Development is not permitted by Class ZA—
(a) if land covered by, or within the curtilage of, the old building—
(i) is occupied in any part under an agricultural tenancy, unless the express consent of both the landlord and the tenant has been obtained;
(ii) is or forms part of article 2(3) land;
(iii) is or forms part of a site of special scientific interest;
(iv) is or forms part of a listed building or land within its curtilage;
(v) is or forms part of a scheduled monument or land within its curtilage;
(vi) is or forms part of a safety hazard area;
(vii) is or forms part of a military explosives storage area; or
(viii) is within 3 kilometres of the perimeter of an aerodrome;
(b) if the old building was constructed after 31 December 1989;
(c) if the footprint of the old building exceeds 1,000 square metres;
(d) if the height of the highest part of the roof of the old building above ground level (not including plant, radio masts and antennae) is greater than 18 metres at any point;
(e) unless the old building has been vacant for a period of at least 6 months immediately prior to the date of the application for prior approval;
(f) if the old building has been rendered unsafe or otherwise uninhabitable by the action or inaction of any person having an interest in the land on which the old building stands and it is practicable to secure safety or health by works of repair or works for affording temporary support (and for this purpose keeping the old building vacant does not of itself count as action or inaction);
(g) if the demolition is “relevant demolition” for the purposes of section 196D of the Act (demolition of an unlisted etc building in a conservation area);
(h) if any of the footprint of the new building falls outside the footprint of the old building;
(i) if any part of the exterior wall of the new building nearest to a highway is nearer to the highway than the part nearest the highway of the exterior wall nearest the highway of the old building;
(j) if the height (not including plant, radio masts and antennae) of the new building would at any point exceed the lower of—
(i) 7 metres above the height (not including plant) of old building; or
(ii) 18 metres, above ground level;
(k) if the new building has more than X + 2 storeys, where “X” is the number of storeys in the old building;
(l) if the new building has more storeys than the old building and the floor to ceiling height of any additional storey in the new building, measured internally, would at any point be greater than the lower of—
(i) the floor to ceiling height, measured internally, of any storey in the old building; or
(ii) 3 metres; or
(m) if the height of any plant on the roof of the new building as measured from the lowest surface of that roof would be greater than the height of any existing plant as measured from the lowest surface of the existing roof on the principal part of the old building.

Conditions

ZA.2.—(1)Development under Class ZA is permitted subject to the following conditions.

(2) Where any development under Class ZA is proposed, development is permitted subject to the condition that before beginning the development, the developer must apply to the local planning authority for prior approval of the authority as to—
(a) transport and highways impacts of the development;
(b) contamination risks in relation to the new building;
(c) flooding risks in relation to the new building;
(d) the design of the new building;
(e) the external appearance of the new building;
(f) the provision of adequate natural light in all habitable rooms of each new dwellinghouse in or comprising the new building;
(g) the impact of the development on the amenity of the new building and of neighbouring premises, including overlooking, privacy and light;
(h) impacts of noise from any commercial premises on the intended occupiers of the new dwellinghouses;
(i) the impact on business and new residents of the development’s introduction of, or increase in, residential use in the area in which the development is to take place;
(j) the impact of the development on heritage and archaeology;
(k) the method of demolition of the old building;
(l) the plans for landscaping of the development, including the planting and maintenance of shrubs and trees; and
(m) any—
(i) air traffic and defence asset impacts of the development, and
(ii) impact that, because of the siting of the new building, the development will have on a protected vista identified in the Directions Relating to Protected Vistas dated 15 March 2012 by the Secretary of State, unless no part of the new building (including plant, radio masts and antennae) occupies airspace not occupied by the old building (including plant, radio masts and antennae).

(3) In sub-paragraph (1)(h), “commercial premises” means any premises in the surrounding area which are normally used for the purpose of any commercial or industrial undertaking which existed on the date of the application under sub-paragraph (2), and includes premises licensed under the Licensing Act 2003176 or any other place of public entertainment.

(4) When the developer applies under sub-paragraph (2), paragraph B (procedure for applications for prior approval under Part 20) applies to the application and the material covered by paragraph B(1A) to B(1C).

(5) Any development under Class ZA is permitted subject to the condition that it must be completed within a period of 3 years starting with the date prior approval is granted.

(6) Any development under Class ZA is permitted subject to the condition that before beginning the development, the developer must provide the local planning authority with a report for the management of the construction of the development, which is acceptable to the authority and sets out the method of demolition, the proposed development hours of operation and how any adverse impact of noise, dust and vibration and traffic on occupiers of the new building and adjoining owners or occupiers will be mitigated, the proposed use of materials, and the plans for the disposal and recycling of waste generated by the development and that in carrying out the development the developer must comply with the report.

(7) The developer must notify the local planning authority of the completion of the development as soon as reasonably practicable after completion.

(8) The notification referred to in sub-paragraph (6) must be in writing and must include—
(a) the name of the developer;
(b) the address or location of the development; and
(c) the date of completion.

(9) Any new dwellinghouse created under Class ZA is to remain in use as a dwellinghouse within the meaning of Class C3 of the Schedule to the 1987 Order and for no other purpose, except to the extent that the other purpose is ancillary to the primary use as a dwellinghouse

 